Kitchen budget
Kitchen Remodel Cost in the Twin Cities
A midrange minor kitchen remodel costs $28,196, a midrange major one $81,187 and an upscale major one $159,220 in the Minneapolis column of the 2025 Cost vs. Value report. Those are modeled job costs from a national report, not Twin Cities quotes, and the report does not label its columns, so reading the first value as Minneapolis is our inference (explained below).
- Sheet
- G-1 of G-7
- Set
- MNRenovate
- Scale
- Not to scale
Checked . This is general information, not a quote or legal advice.
The decision
Pick the Cost vs. Value project closest to your scope, start from its Minneapolis job cost, add a 20 percent reserve, then ask your city for its permit fee, because the report's figures are a starting point and not a quote.
Which path are you on?
Decision diagram: which kitchen path are you on?
- Question 1: will the sink, range or refrigerator move? No leads to the same-footprint path.
- Yes leads to question 2: will a wall come out? No leads to a layout change. Yes leads to a layout change with a structural review first.
Anchors are Minneapolis Cost vs. Value 2025 job costs for a midrange minor and a midrange major kitchen remodel (column inferred, metro-wide). The reserve is a 20 percent rule of thumb from one budgeting article. They are not quotes.
What each path costs
Job cost against resale value, three kitchen projects
Cost vs. Value 2025, Minneapolis column. Metro-wide, midrange and upscale definitions are the report's own. We read the first value in each row as Minneapolis from column order, so treat that as inferred.
Show the numbers as a table
| Project | Job cost | Resale value | Recouped |
|---|---|---|---|
| Minor midrange (same footprint) | $28,196 | $28,466 | 101% |
| Major midrange (layout change) | $81,187 | $49,839 | 61.4% |
| Major upscale (layout change) | $159,220 | $60,973 | 38.3% |
Source: Cost vs. Value 2025, Minneapolis, read 2026-11-06. Resale value is what an agent panel says the project adds. It is not an appraisal.
Wayzata permit, plan review and surcharge for each kitchen path
Wayzata's 2026 fee schedule applied to each path's Cost vs. Value job cost. Wayzata lists plan review at 35% for a residential interior remodel and 65% as its general rate, so the layout change is shown both ways. Plymouth and Minnetonka could not be read.
- Building permit
- Plan review
- State surcharge
The permit fee is small beside the build. The extra trade permits a moved sink or range brings are not in these figures. Work out your own city and value. For a sense of what applicants declare, 1,168 Minneapolis kitchen permits from 2023 to 2025 gave a median of $40,000, with the middle half between $15,465 and $82,000. Declared values are not prices. See what the permit record shows.
Permit cost for the same $60,000 kitchen, 16 metro cities
From our permit study. Filled dots use a 2025 or 2026 schedule, hollow dots an older one that may have been replaced. The 14 recent cities run $1,081 (Corcoran) to $1,575 (Apple Valley).
Show every city as a list
- Corcoran (2026): $1,081.46
- Wayzata (2026): $1,134.64
- Maple Grove (2026): $1,219.24
- Coon Rapids (2026): $1,249.76
- Blaine (2026): $1,278.64
- Lakeville (2026): $1,278.64
- Golden Valley (2025): $1,313.89
- Bloomington (2026): $1,324.72
- Maplewood (2026): $1,420.72
- Burnsville (2026): $1,430.27
- Lake Elmo (2026): $1,430.27
- Spring Lake Park (2026): $1,430.27
- Oakdale (2026): $1,567.20
- Apple Valley (2026): $1,575.23
- Minneapolis (2019): $1,773.23
- Saint Paul (2023): $1,815.30
What we would do, by situation
A reading of the sources below, not a quote and not a contractor's advice.
| If this is you | Path | Budget starting point | Do this first |
|---|---|---|---|
| The layout works. You want new cabinets, counters, floors and appliances. | Same footprint | $28,196 anchor, $33,835 with a 20% reserve | Say "same footprint" on the first call. It narrows which firms fit and keeps most work inside one building permit. |
| The sink, range or fridge would work better somewhere else, or you want an island. | Layout change | $81,187 anchor, $97,424 with a 20% reserve | Ask each firm which trades it will use and which permits it will apply for. Moved plumbing, gas and venting carry their own permits. |
| You want to open the kitchen to the next room. | Layout change plus structure | $81,187 anchor or more; structural work is not priced here | Get a structural review before anything else. Ask who sizes the beam and whether an engineer stamps it. |
| You plan to sell within a few years. | Same footprint | Minneapolis recoup 101% against 61.4% for a major midrange remodel (2025, inferred column) | That is one agent-panel opinion, not a promise. Ask a local agent about your own street. |
| Your house was built before 1978. | Either, with a bigger reserve | One budgeting article suggests up to 30% above the projected cost for surprises in older homes | Ask for EPA lead-safe certification and how each bid handles unknown conditions. |
Kitchen remodel cost in the Twin Cities: the sourced numbers
The table is the Minneapolis page of the 2025 Cost vs. Value report. Cost vs. Value is a national report of 28 remodeling projects. Its job costs start from a national price index and are adjusted for each metro with Verisk local building-cost data. Its resale values come from a survey of more than 6,000 Realtors 18.
What the Minneapolis column is: the page prints three values per row and does not label them. Section headings above the table read Minneapolis, West North Central Region and National Averages 1. We read the values in that order. The third value in each kitchen row equals the national-average row on the report's national page ($28,458, $82,793 and $164,104 job cost) 12, which supports the reading. Treat the first value as a metro-wide figure for the report's own project definitions, not a Plymouth, Minnetonka or Wayzata figure.
Limits: the report's methodology page does not define the minor, major and upscale kitchen projects and does not say whether job cost includes permits 18. Resale value is what surveyed agents say a project adds to a sale price, not an appraisal. The costvsvalue.com address redirects to the 2025 report on the Journal of Light Construction site; a 2026 edition URL returned 404 on 2026-11-07, so 2025 is the newest we could open.
| Project | Job cost (Minneapolis column) | Resale value | Cost recouped | Resale minus job cost | National average job cost |
|---|---|---|---|---|---|
| Minor kitchen remodel, midrange | $28,196 | $28,466 | 101% | +$270 | $28,458 |
| Major kitchen remodel, midrange | $81,187 | $49,839 | 61.4% | -$31,348 | $82,793 |
| Major kitchen remodel, upscale | $159,220 | $60,973 | 38.3% | -$98,247 | $164,104 |
Layout is the first budget decision
If the sink, range and refrigerator stay where they are, much of the work is replacing what is already there. If one of them moves, someone has to run new supply and drain lines, a new circuit, a new gas line or a new exhaust path. Each of those is its own trade, and each adds labor.
City permit rules show the same split. Wayzata says electrical, plumbing and heating or air conditioning work generally need their own permits, and lists kitchen cabinets among the items that do not need a building permit 4. A cabinet swap in the same footprint and a rebuilt layout land in different permit categories. Check your own city, because rules differ.
The Cost vs. Value report prices a midrange minor kitchen remodel and a midrange major kitchen remodel as separate projects, and the Minneapolis job costs are $28,196 and $81,187 1. The gap between them is $52,991 (81,187 minus 28,196). The pages we loaded do not list what each project includes 118, so we cannot say how much of that gap is layout and how much is other scope.
- New supply and drain lines to the moved sink.
- A new circuit, or a new gas line, to the moved range.
- A new exhaust path to the outside.
- Same footprint: cabinets, counters and finishes are replaced where they are.
Same footprint against a layout change
Diagram · generic kitchen plan · not to scale
If you want to keep the layout, say so on the first call, because it changes which remodelers fit and which permits apply.
What moves a kitchen cost up or down
Every item below comes from a source we opened on 2026-11-07. Where the source gives no price, the item says so and leaves the number out.
- Up: bigger scope. The report's midrange major kitchen costs $52,991 more than its midrange minor one in Minneapolis 1. The pages we loaded do not say which scope items explain the gap 18.
- Up: work that needs its own trade permits. Wayzata says electrical, plumbing and heating or air conditioning work generally need their own permits 4, and its fee schedule lists plumbing, gas piping and HVAC permits separately from the building permit 6. We did not price those permits.
- Up: a load-bearing change. The Attorney General's handbook says to confirm a Board of Architecture license if a contractor offers architectural planning or structural design 5. We found no sourced price for structural engineering.
- Up: a higher permit valuation. In Wayzata the building permit rises $8.00 per $1,000 or fraction between $50,000 and $100,000, the valuation counts material and labor, and labor is counted even if you do the work yourself 6. Doing the labor yourself does not lower the permit basis.
- Up: the plan-review rate. Wayzata lists plan review at 35 percent of the permit fee for a residential interior remodel and 65 percent as its general rate 6. On an $81,187 valuation that is $347.99 against $646.26.
- Up: a house built before 1978. EPA's rule requires certified firms and lead-safe practices for paid work that disturbs painted surfaces 3. The EPA page gives no price for it.
- Up: what opens behind the walls. One budgeting article suggests a contingency of 20 percent, and about 30 percent above projected cost for unexpected problems in older homes 10. It is a general-audience source, not a Minnesota standard.
- Up: a low bid that grows later. The Attorney General's handbook warns that charges blamed on unforeseen circumstances can raise a low bid 5.
- Down versus the national figure: location. The report's Minneapolis job costs sit $262, $1,606 and $4,884 below its national averages for the three kitchens above 12. The report attributes local differences to Verisk regional cost data 18.
- Control: a written scope with materials named. The handbook says detailed scope and materials make bids comparable, and advises at least three written bids 5.
Cabinets and lead time
Stock, semi-custom and custom cabinet lines are priced differently, and this guide has no sourced price per cabinet. Get the cabinet line, brand and finish named in writing so every bid prices the same thing.
Cabinets also set the calendar. One cabinet seller's blog gives order-to-delivery ranges of about 1 to 2 weeks for stock ready-to-assemble, 2 to 4 weeks for stock assembled, 4 to 6 weeks for semi-custom and 6 to 12 weeks for most custom orders 9. That source sells cabinets, so treat the ranges as one seller's experience, not an industry standard. It also says spring and the October to December holiday period are busy, and that manufacturers may close one to two weeks around Christmas and New Year's 9.
Taking out a wall is a structural question. Ask who is responsible for the structural sizing and whether an engineer stamps it.
Cabinet order-to-delivery time, by cabinet line
Chart · weeks to scale · one cabinet seller's ranges
Show the numbers as a table
| Cabinet line | Order to delivery |
|---|---|
| Stock, ready-to-assemble | 1 to 2 weeks |
| Stock, assembled | 2 to 4 weeks |
| Semi-custom | 4 to 6 weeks |
| Most custom | 6 to 12 weeks |
What a permit costs: Wayzata as a worked sample
We could not load the Plymouth or Minnetonka fee schedules. Both city sites returned HTTP 403 (access denied) to our tool again on 2026-11-07, and we did not try to get around that, so Plymouth's and Minnetonka's fees are unconfirmed here. Call or visit your city's building department for its current schedule. Wayzata's 2026 building permit fee schedule did load, and we use it as a sample of how a Minnesota city builds the number. Your city's amounts will differ.
Wayzata bases the building permit fee on valuation, meaning material and labor for the whole project, including electrical, gas, mechanical and plumbing, with labor counted even if you do the work 6. Valuations are adjusted if they look wrong 6. The fee for valuations from $25,001 to $50,000 is $450 for the first $25,000 plus $11.75 for each additional $1,000 or fraction. From $50,001 to $100,000 it is $738.25 for the first $50,000 plus $8.00 for each additional $1,000 or fraction 6.
Plan review is a separate line. Wayzata lists plan review at 65 percent of the permit fee, 35 percent for a residential interior remodel and 25 percent for similar plans, plus a state surcharge of 0.0005 of valuation 6. State law sets the plan review baseline at 65 percent of the building permit fee 7, and sets the surcharge at 0.0005 times valuation for projects up to $1,000,000 8. Wayzata also lists sewer and water access charges that apply when applicable 6. We do not know whether a kitchen remodel triggers them.
Wayzata's schedule also lists plumbing, gas piping and HVAC permit fees as based on valuation 6. We did not compute them because we could not tie the formula text we extracted to a residential kitchen.
Worked budget: a midrange kitchen in Wayzata
Two paths, using the Minneapolis column's midrange job costs as the anchor and Wayzata's 2026 permit schedule as the sample permit. Illustration, not a quote.
Permit arithmetic, same-footprint path: building permit $450 + 4 x $11.75 (the $3,196 over $25,000 is 4 started thousands) = $497.00 6; plan review at 35 percent = $173.95; state surcharge 0.0005 x $28,196 = $14.10 68; total $685.05. Layout-change path: $738.25 + 32 x $8.00 (the $31,187 over $50,000 is 32 started thousands) = $994.25 6; plan review $347.99; surcharge $40.59; total $1,382.83. If Wayzata applied its 65 percent general rate instead, plan review would be $323.05 and $646.26, and the totals $834.15 and $1,681.10 6.
The high end adds the reserve and the permit total to the job cost. The report does not say whether its job cost already includes permits 18, so the high end may count permits twice. For an upscale $159,220 kitchen the same arithmetic gives a $31,844 reserve and a Wayzata permit total of $2,144.43 at 35 percent plan review or $2,603.29 at 65 percent.
Plymouth and Minnetonka: fee unconfirmed, as above. Not in these figures: trade permits, structural engineering and design fees, because we found no sourced amounts. The resale line is one survey figure, not a promise of what your house will sell for 1.
| Line | Same footprint (minor midrange) | Layout change (major midrange) |
|---|---|---|
| Job cost, Minneapolis column | $28,196 | $81,187 |
| Reserve, 20 percent of job cost | $5,639 | $16,237 |
| Wayzata building permit | $497.00 | $994.25 |
| Plan review at 35 percent | $173.95 | $347.99 |
| State surcharge | $14.10 | $40.59 |
| Permit total, 35 percent plan review | $685.05 | $1,382.83 |
| Permit total if plan review is 65 percent | $834.15 | $1,681.10 |
| Low end: job cost only | $28,196 | $81,187 |
| High end: job cost + reserve + permit total (35 percent) | $34,520 | $98,807 |
| High end if plan review is 65 percent | $34,669 | $99,105 |
| Resale value in the report | $28,466 | $49,839 |
| Job cost not recouped | None; resale is $270 above cost | $31,348 |
| Plymouth or Minnetonka permit | Fee unconfirmed | Fee unconfirmed |
Older homes, lead paint and the reserve
If your house was built before 1978, EPA's Renovation, Repair and Painting rule covers paid work that disturbs painted surfaces. Firms doing that work must be certified and follow lead-safe practices 3. Homeowners working on their own home are generally exempt, unless they rent part of it, run a child care center there or renovate homes for profit 3. EPA says you can find certified firms through its firm search 3.
Old wiring, plumbing and framing can also surface once walls open. The budgeting article we loaded suggests 20 percent, and about 30 percent above projected cost for unexpected problems in older homes 10. That is one general-audience source, so use it as a prompt for a conversation with your lender or adviser, not as a Minnesota standard.
The Attorney General's handbook warns that a low bid can later grow through charges the contractor blames on unforeseen circumstances 5. Ask how each bid handles unknown conditions, and who approves extra cost in writing before work continues.
Codes that shape the scope
Minnesota adopts the 2018 International Residential Code as part of the State Building Code, with its energy, mechanical, plumbing and electrical chapters replaced by separate Minnesota chapters 14. The smoke and carbon monoxide alarm sections of the residential code stay in force 14. We did not load the text that says when a kitchen remodel triggers alarm upgrades, so ask your building official.
The residential energy code, Minnesota Rules chapter 1322, adopts the residential provisions of the 2012 International Energy Conservation Code with Minnesota amendments 11, effective Feb. 14, 2015 13. Its stated purpose covers new construction, rebuilding, changes and repairs 12. A rulemaking docket shows the Department of Labor and Industry asked for comments on the 2024 International Residential Code energy chapter in February 2026, with no adoption date set 17. For a kitchen, ask your building official whether opening exterior walls or ceilings triggers insulation or air-sealing work. We did not find a loaded source that answers that for remodels.
On contracts and recourse: Minnesota law gives homeowners a lien notice rule, where the prime contractor must put a specific notice in a written contract for residential work 16. Statute 327A.02 sets warranty periods for home improvement work: 1 year for workmanship and materials, 2 years for plumbing, electrical, heating or cooling installation, and 10 years for major construction defects tied to structural changes or additions 15. Read the statute and ask an attorney what applies to your contract.
A realistic timeline, phase by phase
We found no loaded source that gives design or construction durations for Minnesota kitchens, so the table below marks sourced durations and leaves the rest for you to ask each remodeler to state in writing.
Design and selections: no sourced duration. Plan to finish cabinet selections before you sign, because the order cannot be placed until the layout and finish are fixed.
Permit review: Wayzata's page lists no review turnaround times 4. We could not load Plymouth or Minnetonka's pages. Wayzata says plans should be detailed and usually include floor plans, cross sections, elevations, structural details and a window schedule 4. Incomplete plans are the controllable delay.
Cabinet lead time: 1 to 2 weeks for stock ready-to-assemble up to 6 to 12 weeks for most custom, per one seller 9. That seller says missing the carrier's scheduling call can add 3 to 5 days, and one missing piece can hold up a whole order 9.
Construction: no sourced duration. Countertops generally wait on installed cabinets, so ask the remodeler for a sequence, not just a total number of weeks.
Winter has a small effect on interior kitchens compared with additions, but delivery and holiday closures matter. The seller's note on holiday closures and busy seasons is the sourced piece here 9.
Decide this before you call anyone
Work in this order, and write each answer down before the first call.
- Step 1: pick the Cost vs. Value project closest to your scope: minor midrange ($28,196 in the Minneapolis column), major midrange ($81,187) or major upscale ($159,220) 1. The report's pages we loaded do not define the projects, so compare your scope with what the report says about each.
- Step 2: decide whether the cabinets stay, and which line you want: stock, semi-custom or custom. Pick the one whose lead time fits your date 9.
- Step 3: decide whether any wall comes out. If it might, budget for a structural review before you budget anything else.
- Step 4: add a reserve. The loaded source recommends 20 percent as its own line 10. If the house predates 1978, ask about lead-safe certification 3.
- Step 5: ask your city for its current permit fee schedule and review time. Use the Wayzata table above as a template, not as your number. Plymouth and Minnetonka fees are unconfirmed here.
- Step 6: write a scope with materials named. The Attorney General's handbook says detailed scope and materials make bids comparable 5. Ask for at least three written bids 5.
This page does not establish Plymouth or Minnetonka fees, review times, design or construction durations, or what your house will cost.
Sources
- 1Cost vs. Value 2025, Minneapolis, Minnesota. Zonda / Journal of Light Construction. Accessed .
- 2Cost vs. Value Report 2025 (national averages; costvsvalue.com redirects here). Zonda / Journal of Light Construction. Accessed .
- 3Renovation, Repair and Painting Program. U.S. Environmental Protection Agency. Accessed .
- 4Permits & Licensing. City of Wayzata. Accessed .
- 5Home Building and Remodeling Handbook, Choosing a Contractor. Minnesota Attorney General. Accessed .
- 62026 Building Permit Fee Schedule (Wayzata Approved Fee Schedule). City of Wayzata. Accessed .
- 7Minnesota Statutes 326B.153, Fees. Minnesota Office of the Revisor of Statutes. Accessed .
- 8Minnesota Statutes 326B.148, Surcharge. Minnesota Office of the Revisor of Statutes. Accessed .
- 9Kitchen Cabinet Lead Times (seller blog). Kitchen Cabinet Kings. Accessed .
- 10Home Improvement Budgeting. Today's Homeowner. Accessed .
- 11Minnesota Rules 1322.0010, Adoption of the International Energy Conservation Code. Minnesota Office of the Revisor of Statutes. Accessed .
- 12Minnesota Rules 1322.0015, Administration and purpose. Minnesota Office of the Revisor of Statutes. Accessed .
- 132020 Minnesota Residential Energy Code (code book fact sheet). Minnesota Department of Labor and Industry. Accessed .
- 14Minnesota Rules 1309.0010, Adoption of the International Residential Code. Minnesota Office of the Revisor of Statutes. Accessed .
- 15Minnesota Statutes 327A.02, Warranties. Minnesota Office of the Revisor of Statutes. Accessed .
- 16Minnesota Statutes 514.011, Notice required for residential work. Minnesota Office of the Revisor of Statutes. Accessed .
- 17Rulemaking Docket for Minnesota Rules Chapter 1322. Minnesota Department of Labor and Industry. Accessed .
- 18Cost vs. Value 2025 methodology. Zonda / Journal of Light Construction. Accessed .
Provenance
How this was made
- Primary sources
- Cost vs. Value 2025, Minneapolis, MinnesotaZonda / Journal of Light Construction
- Cost vs. Value Report 2025 (national averages; costvsvalue.com redirects here)Zonda / Journal of Light Construction
- Renovation, Repair and Painting ProgramU.S. Environmental Protection Agency
- Permits & LicensingCity of Wayzata
- Home Building and Remodeling Handbook, Choosing a ContractorMinnesota Attorney General
- 2026 Building Permit Fee Schedule (Wayzata Approved Fee Schedule)City of Wayzata
- Minnesota Statutes 326B.153, FeesMinnesota Office of the Revisor of Statutes
- Minnesota Statutes 326B.148, SurchargeMinnesota Office of the Revisor of Statutes
- Date checked
- Method
- Facts come from the numbered sources above, read on the date shown. Arithmetic is written out in the text so you can redo it. Figures from a report or a seller are labeled as that, and anything we inferred, such as which column of a table is which, is said to be inferred. The charts above use the same numbers as the text and the permit study, and the permit amounts are computed by the same code as the permit calculator.
- What is still unknown
- Whether the report labels the Minneapolis column. It prints no labels, and we read the first value as Minneapolis. The 2025 edition is the newest we could open.
- What each Cost vs. Value kitchen project includes. The pages we loaded do not define them.
- Plymouth and Minnetonka permit fees and review times. Both city sites refused our tool on 2026-11-07.
- What structural engineering and trade permits cost.
- Whether the report's job costs already include permit fees.
- What your own house will cost. No figure here is a quote.
- Spot a mistake?
- Tell us at rice.john.nextgenai@gmail.com. We review every correction and, when the record supports it, fix the page and date the change.